LAHORE: Chinese companies building the 1,320MW Sahiwal coal-fired power plant, the first-ever such a project in Pakistan, expect power generation next year which will be the ‘cheapest’ in terms of tariff and environment friendly.

Though the consortium of two Chinese companies which started work on June 9, 2015, is raising basic infrastructure at over a thousand acre land reserved for the plant with an official target of completing it by Dec 25, 2017, officials say the provincial chief executive wants it to be completed much earlier.

Around 3,000 workers, including 1,000 Chinese, are working at the site which is guarded by police personnel.

“We are going to offer 8.1 cents per electricity unit to the Pakistani government under an agreement with the National Electric Power Regulatory Authority and this is the cheapest rate in Pakistan”, says Song Taiji, the Chief Executive Officer of Humeng Shandong Ruyi (Pakistan) Energy (Pvt) Limited.

He told Lahore-based reporters at the site on Friday that the company would produce and sell the electricity for 30 years on a BOT basis before handing over the plant to the Punjab government. He said average life of the plant was 30 years approximately.

Song said the upfront tariff was agreed after Nepra involved international experts and bidding process. He said the plant was being constructed with an estimated cost of $1.8 billion jointly sponsored by two Chinese companies.

He said the coal-fired power generation was much popular in China as more than 80 per cent electricity production came from coal there.

Song said the reason behind importing coal from Indonesia and South Africa was the non-availability of standard coal in Pakistan. “Though Pakistan has huge reserves of indigenous coal but we cannot use them at the moment because of absence of excavation technology and quality material”, he added.

He said the coal would be transported from Port Qasim, Karachi, to the site via rail while canal water with the help of a reservoir would be used in the power generation process. To a question, Song claimed the solar power was costlier than coal’s.

He said the super critical technology would be used in the plant which required high temperature for the perimeter of steam and less coal consumption.

Regarding environmental concerns, he said the height of the Chimney had been set at 180 meters for safe emission.

He said two per cent component of sulphur dioxide in the imported coal would be brought down to zero level to avoid environmental hazards. “We will have proper sulphurization process in the plant for less carbon emission.”

Song further said plants having capacity of more than 300MW fell in the category of super critical technology, adding in Pakistan the coal generation share was even less than one per cent compared to developed countries where share of electricity from coal was about 50 per cent, which meant more environmental pollution.

Song, whose company is the largest in China to generate coal-fired electricity, said he had security concerns before coming to Pakistan last year but now he was comfortable.

“We now feel secure in Punjab and will continue our work without any fear. I rate Pakistan as my second hometown”, Song told a questioner.

Asked why coal-fired technology was being introduced in Punjab when it was becoming redundant in other countries of the world, he said coal-fired power was not an old-fashioned rather it was very advance technology being used by China and other countries.

“This plant is not sub-critical rather super critical which burns less coal and gives less emission as for as environmental protection is concerned.”

Nadeem Aslam Chauhdry, who is energy coordinator for the Punjab government, told reporters that the chief minister had asked the company to complete the plant much earlier than the deadline. “We cannot give you the exact date but we are determined to do the job in less than two and half years.”

He said the federal government had announced upfront tariff for the coal power projects and the company had accepted the tariff of 8.1 cents per unit irrespective of its cost estimates.

He claimed the tariff would not remain exactly 8.1 cents in future as, at the time of agreement, the cost of coal was $ 120 per ton and it was now $60 per ton which implied that the power tariff was the cheapest for this plant as compared to other fossil fuels.

Chauhdry told a questioner that an army brigade was being raised to secure projects linked with the China Pakistan Economic Corridor and this power plant also included in the CPEC.

Sahiwal coal-fired power plant: Builders expect power generation before deadline - Pakistan - DAWN.COM
 
Well hopefully we will be successfull to at least reduce short fall by 2017 if not finish it completely. Our next step should be either to phase out IPP or covert them to either coal or LPG based power generation

Bhasha and Dhasu are critical if we want to end Energy short fall by 2025.
 
Insha Allah Load Shedding will be reduced to quiet extent in 2017
 
Well hopefully we will be successfull to at least reduce short fall by 2017 if not finish it completely. Our next step should be either to phase out IPP or covert them to either coal or LPG based power generation

Bhasha and Dhasu are critical if we want to end Energy short fall by 2025.

Why not just build more and more coal plants if they're taking only 2 years to complete?
 
Why not just build more and more coal plants if they're taking only 2 years to complete?

1 in Sahiwal
1 in Karachi Port Qasim
1 in Salt range near kalar kahar
1 near Lahore
1 in Muzaffargarh
2 in thar
1 in rahim yar khan

there's also news about coal power projects in Lahore Multan Faisalabad Chinot

CPEC.jpg
 
Has construction started in these areas yet or are they still in everlasting planning stage?

Thar Power Plant
under construction, currently 1 MW is being produced by underground coal gasification process, generation will be enhanced to 100 MW by the end of 2016.


Siddique sons Energy Limited 350 MW
Private coal-based power project, PPIB has issued a letter of support, estimated to cost $600 million and be completed by first quarter of 2016

Jamshoro Coal power Project 600 MW
Under construction, a $1.5 billion joint venture of IDB ADB and GOP
IDB approves $220m for Jamshoro power project - Pakistan - DAWN.COM

K Electric Coal Power Plant 600 MW
Under construction by K-Electric and China's Harbin Electric International (HEI)

Thar Power Plant II 600 MW
Under construction; project involves development of mining at Thar Coal Block-II

120 MW power plant in Muzaffargarh
under construction. An energy unit is being executed with the Chinese assistance at a sugar mill, to produce 120 megawatt electricity from coal and sugarcane husk, to be completed by February 2016, at a cost of 27 billion rupees
International cooperation: China to help set up bio-tech lab in Multan - The Express Tribune


Port Qasim Coal power Plant 1320 MW
Under construction since May 2014, a joint venture of China's Powerchina and Qatar's Al-Mirqab Group
10150649_513025425532679_121450565173714796_n.jpg


Sahiwal Coal Power Plant 1320 MW
Under construction since May 2014 with China's help, Punjab's first coal power plant will be completed by 2016

CUAn425WUAA_dER.jpg

CUAoLgyWsAECgOk.jpg



Hub Coal Power Project
Under construction, In January 2015, HUBCO announced that it would set up 1,320MW coal-based power plants next to its thermal power station at Hub in Balochistan and gradually enhance coal based generation to 3,600MW
Hubco plans to set up 3,600 MW coal power plants at Hub Balochistan | Customs Today Newspaper



Maple Leaf Power Limited Mianwali 40 MW
Under construction, In Dec 2015, Maple Leaf Cement announced that it would set up 40MW coal-based power plant, which will be functional by May 2017
 
Great news. The trolls are understandably absent from this topic.
 
Thar Power Plant
under construction, currently 1 MW is being produced by underground coal gasification process, generation will be enhanced to 100 MW by the end of 2016.


Siddique sons Energy Limited 350 MW
Private coal-based power project, PPIB has issued a letter of support, estimated to cost $600 million and be completed by first quarter of 2016

Jamshoro Coal power Project 600 MW
Under construction, a $1.5 billion joint venture of IDB ADB and GOP
IDB approves $220m for Jamshoro power project - Pakistan - DAWN.COM

K Electric Coal Power Plant 600 MW
Under construction by K-Electric and China's Harbin Electric International (HEI)

Thar Power Plant II 600 MW
Under construction; project involves development of mining at Thar Coal Block-II

120 MW power plant in Muzaffargarh
under construction. An energy unit is being executed with the Chinese assistance at a sugar mill, to produce 120 megawatt electricity from coal and sugarcane husk, to be completed by February 2016, at a cost of 27 billion rupees
International cooperation: China to help set up bio-tech lab in Multan - The Express Tribune


Port Qasim Coal power Plant 1320 MW
Under construction since May 2014, a joint venture of China's Powerchina and Qatar's Al-Mirqab Group
10150649_513025425532679_121450565173714796_n.jpg


Sahiwal Coal Power Plant 1320 MW
Under construction since May 2014 with China's help, Punjab's first coal power plant will be completed by 2016

CUAn425WUAA_dER.jpg

CUAoLgyWsAECgOk.jpg



Hub Coal Power Project
Under construction, In January 2015, HUBCO announced that it would set up 1,320MW coal-based power plants next to its thermal power station at Hub in Balochistan and gradually enhance coal based generation to 3,600MW
Hubco plans to set up 3,600 MW coal power plants at Hub Balochistan | Customs Today Newspaper



Maple Leaf Power Limited Mianwali 40 MW
Under construction, In Dec 2015, Maple Leaf Cement announced that it would set up 40MW coal-based power plant, which will be functional by May 2017

Good work brother. Do you keep a table of these programs under construction?
 
As per sources Lahore Power Plant project has been scrapped due to some asshole's (plz ignore my words) objections :hitwall::hitwall:
 
Good work brother. Do you keep a table of these programs under construction?

Yupe i keep a table and a map of these projects Weather it's DAMS RLNG WIND SOLAR NUCLEAR COAL or THERMAL

As per sources Lahore Power Plant project has been scrapped due to some asshole's (plz ignore my words) objections :hitwall::hitwall:

Same was about to happen on Karachi nuclear plants but we got Lucky on that :P
 
environment friendly.

Coal fired plants are not environmentally friendly. No matter, which way you spin it.

the company would produce and sell the electricity for 30 years on a BOT basis before handing over the plant to the Punjab government. He said average life of the plant was 30 years approximately.

Lets, analyze shall we: They (private company) will build it and run it for 30 years, then at the end of its life, we will inherit the cleanup cost, I am willing to bet, second grade failed geniuses are signing up these deals.

Goods produced, using coal power will be expensive, as they will Cary carbon tax, making our goods in the world markets extremely expensive.
 
Yupe i keep a table and a map of these projects Weather it's DAMS RLNG WIND SOLAR NUCLEAR COAL or THERMAL



Same was about to happen on Karachi nuclear plants but we got Lucky on that :P





It is not good for a country like a Pakistan where first of all due to lack capital Projects remain in the files and when we got investor we have problems. Actually Pakistani as a Nation has some inferiority complex or they are jealous that these projects are inaugurated by PMLN. People find excuses to derail the projects. From corruption's point of view, i think it is most important that project get completed and delivered output. kick backs always happen in big projects even in first world countries like Germany where ministers were also involved in VW scandal.
 