What's new

India Developing, but still a long way to go

Hyderabad metro rail creates record; completes 27 km, 1,000 spans in 20 months

View attachment 40967

The significance of record can be measured by the fact that Mumbai Metro Rail took about seven years to complete 11 km of metro viaduct; Bangalore and Chennai took over five years to complete about 25 km of viaduct each. Delhi took more than three years to achieve the same

Metro creates record; completes 27 km, 1,000 spans in 20 months - The Hindu


This is called the learning effect.
 
Hyderabad metro rail creates record; completes 27 km, 1,000 spans in 20 months

View attachment 40967

The significance of record can be measured by the fact that Mumbai Metro Rail took about seven years to complete 11 km of metro viaduct; Bangalore and Chennai took over five years to complete about 25 km of viaduct each. Delhi took more than three years to achieve the same

Metro creates record; completes 27 km, 1,000 spans in 20 months - The Hindu

Mumbai Metro was built by Chor Company that's why it took so long
 
Hyderabad metro rail creates record; completes 27 km, 1,000 spans in 20 months

View attachment 40967

The significance of record can be measured by the fact that Mumbai Metro Rail took about seven years to complete 11 km of metro viaduct; Bangalore and Chennai took over five years to complete about 25 km of viaduct each. Delhi took more than three years to achieve the same

Metro creates record; completes 27 km, 1,000 spans in 20 months - The Hindu


Seriously love L&T. Every damn thing they enter into they make sure to do their damn best!!!

Thats god damn why I want them more in defence manufacturing!!
 
Hyderabad metro rail creates record; completes 27 km, 1,000 spans in 20 months

View attachment 40967

The significance of record can be measured by the fact that Mumbai Metro Rail took about seven years to complete 11 km of metro viaduct; Bangalore and Chennai took over five years to complete about 25 km of viaduct each. Delhi took more than three years to achieve the same

Metro creates record; completes 27 km, 1,000 spans in 20 months - The Hindu


One thing that has always puzzled me. How these individual pieces are joined to to make the complete bridge?
 
One thing that has always puzzled me. How these individual pieces are joined to to make the complete bridge?

Well, those "individual pieces" are pre-cast as opposed to being cast on site. Pre-cast segments (most likely cast close to the construction site to improve transportation logistics) are joined together by (pre-stressed) cables, and are set in place by tension. Notice that all precast segments have holes in them for cables to pass through. Precast segment construction is a more efficient method of of bridge span construction.
 
Hyderabad Airport

7uoi.jpg




vskale,flickr
 
The Fifth train set manufactured from Alstom factory, Sricity, Andhra Pradesh has reached depot. This is the fifth train out of 33 trains to be delivered from Sricity. Unloading and coupling of cars has been initiated.
After preliminary checks, the train will be subjected to non-regression testing at workshop line and then it will be moved to test track for further testing and dynamic trails.

KcNJgeX.jpg


jwDlUxZ.jpg


QdrSHUg.jpg


rN2QIqJ.jpg


0VYhIRx.jpg


MOhx7jC.jpg
 

The façade of this building is stunning and the atrium which serves as the main entrance is six storey high. This building will mainly used for offices and commercial purposes. Manjeera constructions and Gowra group is building this 150 crore joint venture. They also have future plans to build a five star hotel next to it.

P.S. My company got the contract for waterproofing this building because we use ecologically sustainable green products. :yahoo:
 

Latest posts

Back
Top Bottom