What's new

China Pakistan Economic Corridor (CPEC) | Power Plants


..


Concrete works at Suki Kinari hydropower project - Powerhouse

Dasu Hydropower Project Grid Station excavation, Stone pitching & Material dumping in progress.


109870597_158532522469240_214322055857122911_n.jpg






107806801_158532542469238_8022618031184999113_n.jpg







109740424_158532562469236_1715441137226597111_n.jpg
 
Dasu Hydropower Project - 4320MW (2160 MW stage-I)

- Annual Energy: 21,300 GWh
- Gross Storage: 1.14 Million acre-feet (MAF)

- Completion: Early 2025 (stage I)
- Construction cost: $ 4.3 billion (stage I)


109538771_158898895765936_48384064780496948_o.jpg






108777814_158898912432601_3429626266070739568_o.jpg





109349752_158898999099259_2182131007852692475_o.jpg





109510508_158899285765897_7901781241813208551_o.jpg
 
Qasim Plant generates more than 5 billion kWh of electricity in 2020

Qasim Coal Power Plant,
invested and constructed by Power Construction Corporation of China, has generated more than 5 billion kWh in 2020, setting a record for the annual cumulative power generation since the plant was put into operation.

In 2020, the annual generating capacity of Qasim Plant reached 5 billion kilowatts earlier than usual.The 2018 cumulative power generation reached this node in early October of that year, and in 2019 it was moved forward to August 27th.

Impacted by COVID-19 pandemic, national economy has been stuck. Under the severe context, Qasim Plant generated more than 2.264 billion kWh in the first quarter of 2020, an increase of 455 million kWh over the same period last year.

On May 22, 2020 annual power generation of the power station reached 3.5 billion kWh, and the cumulative power generation since its commissioning exceeded 20 billion kWh. As of June 10, the cumulative annual power generation of Kasim Power Station exceeded 4 billion kWh.

In this month, Qasim Plant also saw a breakthrough in expanding the coal sources. Affected by COVID-19 epidemic, South Africa and Indonesia, the two major coal sources for Qasim project, have been port locked down. The continuous operation of the plant is threatened.

In order to protect domestic own coal resources and diversify coal sources, after a long-term endeavour by Qasim project, a new coal source country was established. On July 11th, the first batch of coal imported from the new coal source country reached Qasim Port.

Qasim Coal Power Plant is reckoned as a key project under CPEC. It has an installed capacity of 1.32 million kW and uses imported coal to generate electricity. Since its commissioning, the power station has played an important role in alleviating the power shortage, improving the energy structure, promoting economic and social development and improving people's livelihood for the nation.




110331990_2655851348016716_6109541370510788608_n.jpg





110280510_2655851411350043_384095356428720216_n.jpg
 
The efforts for optimizing and progressing the CPEC based hydropower generation in the country got major push today when the Board of Private Power and Infrastructure Board (PPIB) in its 128th meeting held today under the Minister for Power Mr. Omar Ayub Khan approved "Standardized Security Package Documents for Hydropower Projects" for submission to ECC for final approval.

The said documents have been prepared by PPIB with the consultation of federal and provincial stakeholders to cater for institutional requirements at federal as well as provincial and AJ&K level. This will help in mitigating protracted negotiations with the private investor thus paving way for smooth and timely implementation of hydropower projects. With the approval of these documents from ECC, the specific agreements of 1,124 MW Kohala and 700 MW Azad Pattan Hydropower Projects will stand approved for execution. The Minister appreciated this development and said that the GoP is doing every effort for attracting foreign direct investment in the country and today’s accomplishment is a latest example of GoP’s commitment for improving power supply in the country. With the implementation of these two major hydropower projects under CPEC, more than 8,400 GWh of clean and green energy would be added to the national grid every year. The Minister further stated that the present government is reducing red tapism to fully facilitate the investors for availing the variables of growth and better returns which are available in the energy sector.

The Managing Director PPIB Mr. Shah Jahan Mirza briefed the Board on various ongoing power generation projects being implemented all over the country. The Board was briefed that PPIB is currently processing a diversified portfolio of twenty five power generation projects of around 12,500 MW while strategically important Matiari-Lahore HVDC Transmission Line Project is also part of its active portfolio. The Minister appreciated PPIB’s performance and advised continue playing its role in further streamlining the processes for facilitation of investors and timely completion of pipeline projects.

Courtesy: PPIB

 
Dasu_Hydropower_Project- 4320MW (2160 MW stage-I)

- Annual Energy: 21,300 GWh
- Gross Storage: 1.14 Million acre-feet (MAF)
- Completion: Early 2025 (stage I)
- Construction cost: $ 4.3 billion (stage I)



108008210_159768469012312_7612253941849114188_o.jpg





109739976_159768499012309_5052368956708205271_o.jpg





110119356_159768525678973_977241453998330466_o.jpg
 
Relocation of KKH -01 under DASU HYDROPOWER PROJECT.

The realigned and alternative road is being constructed by WAPDA in place of existing submerged KKH under Dasu HPP.
It will be constructed in two phases KKH-01 and KKH -02.


116153983_160409548948204_7955136000405216514_o.jpg





116440269_160409565614869_5336178421955997501_o.jpg




109555050_160409582281534_3555759012191618887_o.jpg
 
Shanghai Electric has accelerated pace of work despite COVID at Thar Block-1 both in Mining & 1320 MW power plant.

Progress ................ Mining 20%,................. power Plant 15%.


116428320_2916772505117095_7868144797240626638_n.jpg




115825415_2916772661783746_1047316995203893880_o.jpg



116226957_2916772798450399_6908928530199890307_o.jpg
 
720MW Karot_Hydropower_Project is an under construction run-of-river project.

The Karot Hydropower Project is the first investment project of the Silk Road Fund, is part of the much larger CPEC .... China_Pakistan_Economic_Corridor, and is expected to be completed in 2021.
Construction began: January 2016
Construction cost: $1.42 billion
Commission date: Apr 2021
Turbines: 4 x 180 MW Francis-type
Installed capacity : 720 MW
Reservoir Total capacity: 164.5 million
Maximum length: 27 km (17 mi)
Normal elevation: 461 m (1,512 ft)
 
- Annual Energy: 3,000 GWh
- Highest Head in Pakistan
- Completion: Dec, 2022
- Construction cost: $1.9 billion


109038613_157457039243455_4923746571319935633_o.jpg


108021539_157456992576793_7954095115435772015_o.jpg
 
Dasu hydropower project (DHP) includes the construction of a 4,320 MW hydropower plant on the Indus River near Dasu town in Kohistan District of KhyberPakhtunkhwa (KP) .

The project is located approximately 74 km downstream of the Diamer Basha Dam, 240 km upstream of the Tarbela Dam, and 345 km from Islamabad.

The run-of-the-river hydropower project is being developed in two stages by Pakistan’s Water and Power Development Authority (WAPDA).

A total of 12 hydropower units rated at 360 MW each will be installed, which includes six in the first phase and six in the second.

Phase one will have an annual output capacity of 12,300 GWh, while phase two completion would increase the same to 21,700 GWh.

Construction Period (PC-I) is 5 years (Stage-I) with Generation of 2,160 MW (12,220 GWh).
 

Pakistan Affairs Latest Posts

Back
Top Bottom