New Delhi: With the construction of three of the six tunnels, including the strategic Z-Morh tunnel, expected to be completed by mid-2023, road connectivity between Jammu and Kashmir and the rest of India is set to get a big leg up.
Four of the six tunnels are coming up on National Highway-244, connecting Jammu to Anantnag. They are the Khellani tunnel, the KM 83 tunnel, Shuddhmadev-Dranga tunnel and Singhpora-Vailoo tunnel. Once the four tunnels are ready, travel time between Jammu and Anantnag will reduce from the current 11-12 hours to 6 hours.

The remaining two tunnels on NH-1 — the strategically crucial Zojila and Z-Morh — will provide all-weather road connectivity between Srinagar and Kargil.
The National Highways and Infrastructure Development Corporation (NHIDCL), a unit of the Ministry of Road Transport and Highways, is implementing all the six tunnel projects, worth Rs 18,539 crore.

“These tunnels are important from a strategic point of view and will provide round-the-year connectivity between Jammu and Kashmir to the rest of India and will also spur economic activity in the region,” NHIDCL managing director Chanchal Kumar told ThePrint.

Kumar added that the tunnels will not only come as a boost for the security forces, but will also ease travel for civilians.

Currently, during the winter, heavy snowfall frequently disrupts road movement on NH-244, connecting Jammu to Anantnag, and NH-1, connecting Srinagar to Kargil.

JK-Tunnels.jpg

Strategic J & K tunnels under construction| Graphics by: Manisha Yadav | ThePrint


Three tunnels to be ready by 2023

Kumar said the three tunnels likely to be completed next year are Khellani, ‘KM 83’, and Z-Morh. The Khellani tunnel is expected to be ready by May and the ‘KM 83’ tunnel by April.

The Z-Morh tunnel, connecting Srinagar to Sonamarg, is likely to be ready by mid-2023. “Though the official date of completion of the Z-Morh tunnel is December 2023, we are hoping to finish work three-four months before the targeted date,” a senior NHIDCL officer said.

The strategically important 14.15 km tunnel coming up at Zojila, connecting Srinagar to Kargil, is expected to be completed by September 2026. The existing NH-1, connecting Srinagar to Leh, remains shut six months on account of snowfall. Once ready, the Zojila tunnel will reduce the travel time between Srinagar and Leh from 3 hours to barely 15 minutes.

The geo-sensitive Zojila stretch, which is strategically important from defence perspective, will not only provide all-weather connectivity between Srinagar, Drass, Kargil and Leh, but also further strengthen economic and social-cultural integration of both the Union Territories.

Bids for two tunnels on NH-244 soon

NHIDCL will shortly open bids for two more tunnels on NH-244 — the 8 km Shudhmahadev-Dranga tunnel worth Rs 3,703 crore, and the 10.3 km Singhpora-Vailoo tunnel worth Rs 4,808 crore.

“We will open the bids soon and intend to award work on both the projects this fiscal,” Kumar said.

Currently, highway projects worth over Rs 50,000 crore are underway in the region and implemented by agencies including NHIDCL and Border Road Organisation (BRO). The BRO and the Public Works Department in Jammu and Kashmir are implementing over 24 NH projects.


@beijingwalker @applesauce @etylo @MH.Yang @Sam6536 @Skull and Bones @Raj-Hindustani @VkdIndian @DabbuSardar @Abu Shaleh Rumi @Bilal9 @SIPRA @Windjammer @Primus @Trango Towers
@FOOLS_NIGHTMARE
@bluesky

BRO ramping up roads in Arunachal districts along LAC

ANI-20221219161747.jpg

BRO developing bordering areas in Arunachal Pradesh to counter China's aggressive behaviour towards LAC (Photo/ANI)

Tezpur (Assam) [India], December 19 (ANI): The Border Roads Organization (BRO) is engaged in major infrastructural development works along the bordering areas and the government has planned to connect all bordering villages of Arunachal Pradesh with good connectivity roads.

Apart from the road connectivity, the BRO is engaging in construction works of two important tunnels in Arunachal Pradesh’s Tawang and West Kameng districts which will become the game changer for the Indian security forces in view of security issues towards the international border.
ANI-20221219112139.jpeg

The BRO has engaged in all infrastructural development works under Project Vartak.

According to the officials, the constitution works of the Nechiphu Tunnel, at an altitude of 5,700 feet, is a unique 500-metre-long “D-shaped, Single Tube Double Lane Tunnel” on the Balipara-Charduar-Tawang (BCT) road in West Kameng district, is nearby of completion and the construction works of the Sela Pass tunnel will also be completed in next 5-6 months.
ANI-20221219112043.jpeg

The Nechiphu tunnel will accommodate two-way traffic and will be equipped with modern lighting and safety facilities and the tunnel has been conceived to bypass extreme foggy conditions prevailing around Nechiphu Pass which have caused hindrance to general traffic and military convoys for many decades.

The Nechiphu tunnel will be provided with a state-of-the-art electro-mechanical system including firefighting devices, an auto illumination system and Supervisory Control and Data Acquisition (SCADA) controlled monitoring systems and it will also accommodate raised footpaths on both sides for safer pedestrian movement which will have ducts for power cables, optical fibre cables and utility lines to strengthen the civic amenities infrastructure.
ANI-20221219112027.jpeg

Under Project Vartak the BRO is also engaged in the construction works of another strategic tunnel, the Twin Tube (1,555 meters and 980 meters) “The Sela Tunnel Project” on the same road.

In an exclusive interview with ANI, Brig Raman Kumar, Chief Engineer, Vartak said that heavy vehicle movement is hampered in the current Sela Pass road during the winter season.

“Now with the construction of the Sela Pass tunnel traffic will be allowed throughout the year. The heavy vehicles whether it is security forces or private industry equipment which is moving to the area will be able to pass easily through the Sela tunnel and accessibility to Tawang will be opened up. As well as it will boost tourism. It is a very important tunnel. The BRO is very happy and proud to give this to the nation,” Brig Raman Kumar said.

He also said that apart from the roads we are having two important tunnels.

“Sela tunnel is under construction and it is about 400 meters below the Sela Pass. We have two tunnels in that alignment. Once that tunnel is completed, we will have throughout the winters also people would be able to pass through the Sela Pass and it will provide good connectivity in the Tawang district. Another tunnel we are having is at Nechiphu. Apart from it, we have bridges, helipads and so many other works which are helped in the overall development of the Tawang district,” Brig Raman Kumar said.

He further said that the Nechiphu tunnel is almost near completion and we are doing the finishing line of the road work. In the next 2-3 months, the Nechiphu tunnel will be opened for public, civilian traffic. The Sela Pass tunnel, it’s a long tunnel – one tunnel is 1590 meter long tunnel and another is almost a kilometre in length the condition in that area is very tough, but BRO is working overnight and 24-hour works are going on and our task is to open the tunnel for the public as earliest as possible.

“In the next 4-6 months we will be able to open the Sela tunnel. We are constructing several permanent bridges in Arunachal Pradesh. Many other bridges are in pipeline,” Brig Raman Kumar said.

The Chief Engineer of Project Vartak said that the BRO is developing and maintaining in all the road networks in important border areas.

“We are part of project Vartak and we are looking after in Western Assam and Western Arunachal Pradesh areas. We have important National Highway double lane roads, and other types of roads and our aim is to connect each and every village in far furlong areas of West Kameng and Tawang district of Arunachal Pradesh. We want to actively contribute to the socio-economic development of this area. The terrain in this area is very difficult. There are mountainous terrain and high altitude terrain. The mountains are very tough and the climate conditions are very tough. The BRO is working round the clock to provide connectivity in difficult and harsh climatic conditions. There are some remote villages and we are also providing roads to the remote villages. There is no area which is not developed part of the Western Arunachal,” Brig Raman Kumar said. (ANI)
 
Last edited:

India revamps defence infra with army tank ramps, fortification of BSF bunkers at IB in J&K​

jammu-border-security-force-bsf-personnel-patrol-near-the-india-pakistan-bord-.jpg

Indian security agencies have carried out a major defence infrastructure revamp including creation of ramps for army tanks and strengthening of BSF bunkers along the International Border with Pakistan, since the two sides announced a military ceasefire in 2021, officials said.

The first phase of the infrastructure renovation and creation of some new ones has been recently completed on a stretch of 26 kilometres along the front in Jammu while another 33 kilometres in the same region is being carried out, official sources told PTI.

Jammu shares a 192 km-long front of the total 2,289 kilometres of the India -Pakistan IB before it runs down towards Gujarat and Rajasthan on the country's western flank.

The Line of Control (LoC) between the two neighbours falls majorly in Kashmir and it is about 772 kilometres long.

The defence infrastructure work that has been undertaken includes creation and revamp of multiple DCBs (ditch-cum-bandhs), maintenance of damaged border fence, creation of ramps for movement of army tanks to the forward areas, upgrade of Border Security Force 'morchas' (troop posts), bunkers and locations for installation of surveillance and other protection mechanism, officials said.

The work is being undertaken through the funds received from the Union Home ministry, they said.

Officials said these works were initiated and the first phase was completed (on 26 kms) after India and Pakistan renewed their ceasefire agreement along the front in Jammu and Kashmir on February 20, 2021.

"The other side too is undertaking similar works and both sides keep each other informed in case a major work is undertaken near the fence," a senior BSF officer said.

Barring a few violations, like when Pakistan breached the agreement and opened unprovoked fire in Jammu on September 6, Last year's ceasefire agreement is holding well, officials said.

The ceasefire breach took place when the Indian side was undertaking some "maintenance work" in the Arnia sector of Jammu. A flag meeting was later held between the BSF and Pak Rangers and it was decided to uphold the ceasefire.

The silence of the guns is allowing peace to prevail along the IB and border residents and farmers are able to do their normal work uninterrupted and without fearing about flying mortar shells and indiscriminate gunfire undertaken by the other side regularly (before February 20, 2021), officials said.

Work is also being undertaken to level the 'kuttcha' or mud tracks that are used by BSF troop carrier vehicles to reach border posts in Jammu region. At many places, the levelling work on these approach routes has been completed, officials said.

A similar work has been undertaken by the BSF along the Line of Control (LoC) in Kashmir region where it is converting the bunkers for its troops at 115 forward defence locations (FDLs) from the present CGI (corrugated galvanised iron) to solar powered compartments made of steel.

The 772 kilometre-long LoC is guarded by the Army and the BSF is deployed in about 435 kms of this front under its operational command.
 
TUNNEL.jpg

File photo of Zojila and Z-Morh tunnels | ANI

New Delhi: With the construction of three of the six tunnels, including the strategic Z-Morh tunnel, expected to be completed by mid-2023, road connectivity between Jammu and Kashmir and the rest of India is set to get a big leg up.
Four of the six tunnels are coming up on National Highway-244, connecting Jammu to Anantnag. They are the Khellani tunnel, the KM 83 tunnel, Shuddhmadev-Dranga tunnel and Singhpora-Vailoo tunnel. Once the four tunnels are ready, travel time between Jammu and Anantnag will reduce from the current 11-12 hours to 6 hours.

The remaining two tunnels on NH-1 — the strategically crucial Zojila and Z-Morh — will provide all-weather road connectivity between Srinagar and Kargil.
The National Highways and Infrastructure Development Corporation (NHIDCL), a unit of the Ministry of Road Transport and Highways, is implementing all the six tunnel projects, worth Rs 18,539 crore.

“These tunnels are important from a strategic point of view and will provide round-the-year connectivity between Jammu and Kashmir to the rest of India and will also spur economic activity in the region,” NHIDCL managing director Chanchal Kumar told ThePrint.

Kumar added that the tunnels will not only come as a boost for the security forces, but will also ease travel for civilians.

Currently, during the winter, heavy snowfall frequently disrupts road movement on NH-244, connecting Jammu to Anantnag, and NH-1, connecting Srinagar to Kargil.

JK-Tunnels.jpg

Strategic J & K tunnels under construction| Graphics by: Manisha Yadav | ThePrint


Three tunnels to be ready by 2023

Kumar said the three tunnels likely to be completed next year are Khellani, ‘KM 83’, and Z-Morh. The Khellani tunnel is expected to be ready by May and the ‘KM 83’ tunnel by April.

The Z-Morh tunnel, connecting Srinagar to Sonamarg, is likely to be ready by mid-2023. “Though the official date of completion of the Z-Morh tunnel is December 2023, we are hoping to finish work three-four months before the targeted date,” a senior NHIDCL officer said.

The strategically important 14.15 km tunnel coming up at Zojila, connecting Srinagar to Kargil, is expected to be completed by September 2026. The existing NH-1, connecting Srinagar to Leh, remains shut six months on account of snowfall. Once ready, the Zojila tunnel will reduce the travel time between Srinagar and Leh from 3 hours to barely 15 minutes.

The geo-sensitive Zojila stretch, which is strategically important from defence perspective, will not only provide all-weather connectivity between Srinagar, Drass, Kargil and Leh, but also further strengthen economic and social-cultural integration of both the Union Territories.

Bids for two tunnels on NH-244 soon

NHIDCL will shortly open bids for two more tunnels on NH-244 — the 8 km Shudhmahadev-Dranga tunnel worth Rs 3,703 crore, and the 10.3 km Singhpora-Vailoo tunnel worth Rs 4,808 crore.

“We will open the bids soon and intend to award work on both the projects this fiscal,” Kumar said.

Currently, highway projects worth over Rs 50,000 crore are underway in the region and implemented by agencies including NHIDCL and Border Road Organisation (BRO). The BRO and the Public Works Department in Jammu and Kashmir are implementing over 24 NH projects.


@beijingwalker @applesauce @etylo @MH.Yang @Sam6536 @Skull and Bones @Raj-Hindustani @VkdIndian @DabbuSardar @Abu Shaleh Rumi @Bilal9 @SIPRA @Windjammer @Primus @Trango Towers
@FOOLS_NIGHTMARE
@bluesky

BRO ramping up roads in Arunachal districts along LAC

ANI-20221219161747.jpg

BRO developing bordering areas in Arunachal Pradesh to counter China's aggressive behaviour towards LAC (Photo/ANI)

Tezpur (Assam) [India], December 19 (ANI): The Border Roads Organization (BRO) is engaged in major infrastructural development works along the bordering areas and the government has planned to connect all bordering villages of Arunachal Pradesh with good connectivity roads.

Apart from the road connectivity, the BRO is engaging in construction works of two important tunnels in Arunachal Pradesh’s Tawang and West Kameng districts which will become the game changer for the Indian security forces in view of security issues towards the international border.
ANI-20221219112139.jpeg

The BRO has engaged in all infrastructural development works under Project Vartak.

According to the officials, the constitution works of the Nechiphu Tunnel, at an altitude of 5,700 feet, is a unique 500-metre-long “D-shaped, Single Tube Double Lane Tunnel” on the Balipara-Charduar-Tawang (BCT) road in West Kameng district, is nearby of completion and the construction works of the Sela Pass tunnel will also be completed in next 5-6 months.
ANI-20221219112043.jpeg

The Nechiphu tunnel will accommodate two-way traffic and will be equipped with modern lighting and safety facilities and the tunnel has been conceived to bypass extreme foggy conditions prevailing around Nechiphu Pass which have caused hindrance to general traffic and military convoys for many decades.

The Nechiphu tunnel will be provided with a state-of-the-art electro-mechanical system including firefighting devices, an auto illumination system and Supervisory Control and Data Acquisition (SCADA) controlled monitoring systems and it will also accommodate raised footpaths on both sides for safer pedestrian movement which will have ducts for power cables, optical fibre cables and utility lines to strengthen the civic amenities infrastructure.
ANI-20221219112027.jpeg

Under Project Vartak the BRO is also engaged in the construction works of another strategic tunnel, the Twin Tube (1,555 meters and 980 meters) “The Sela Tunnel Project” on the same road.

In an exclusive interview with ANI, Brig Raman Kumar, Chief Engineer, Vartak said that heavy vehicle movement is hampered in the current Sela Pass road during the winter season.

“Now with the construction of the Sela Pass tunnel traffic will be allowed throughout the year. The heavy vehicles whether it is security forces or private industry equipment which is moving to the area will be able to pass easily through the Sela tunnel and accessibility to Tawang will be opened up. As well as it will boost tourism. It is a very important tunnel. The BRO is very happy and proud to give this to the nation,” Brig Raman Kumar said.

He also said that apart from the roads we are having two important tunnels.

“Sela tunnel is under construction and it is about 400 meters below the Sela Pass. We have two tunnels in that alignment. Once that tunnel is completed, we will have throughout the winters also people would be able to pass through the Sela Pass and it will provide good connectivity in the Tawang district. Another tunnel we are having is at Nechiphu. Apart from it, we have bridges, helipads and so many other works which are helped in the overall development of the Tawang district,” Brig Raman Kumar said.

He further said that the Nechiphu tunnel is almost near completion and we are doing the finishing line of the road work. In the next 2-3 months, the Nechiphu tunnel will be opened for public, civilian traffic. The Sela Pass tunnel, it’s a long tunnel – one tunnel is 1590 meter long tunnel and another is almost a kilometre in length the condition in that area is very tough, but BRO is working overnight and 24-hour works are going on and our task is to open the tunnel for the public as earliest as possible.

“In the next 4-6 months we will be able to open the Sela tunnel. We are constructing several permanent bridges in Arunachal Pradesh. Many other bridges are in pipeline,” Brig Raman Kumar said.

The Chief Engineer of Project Vartak said that the BRO is developing and maintaining in all the road networks in important border areas.

“We are part of project Vartak and we are looking after in Western Assam and Western Arunachal Pradesh areas. We have important National Highway double lane roads, and other types of roads and our aim is to connect each and every village in far furlong areas of West Kameng and Tawang district of Arunachal Pradesh. We want to actively contribute to the socio-economic development of this area. The terrain in this area is very difficult. There are mountainous terrain and high altitude terrain. The mountains are very tough and the climate conditions are very tough. The BRO is working round the clock to provide connectivity in difficult and harsh climatic conditions. There are some remote villages and we are also providing roads to the remote villages. There is no area which is not developed part of the Western Arunachal,” Brig Raman Kumar said. (ANI)

good development for the local people.
 
TUNNEL.jpg

File photo of Zojila and Z-Morh tunnels | ANI

New Delhi: With the construction of three of the six tunnels, including the strategic Z-Morh tunnel, expected to be completed by mid-2023, road connectivity between Jammu and Kashmir and the rest of India is set to get a big leg up.
Four of the six tunnels are coming up on National Highway-244, connecting Jammu to Anantnag. They are the Khellani tunnel, the KM 83 tunnel, Shuddhmadev-Dranga tunnel and Singhpora-Vailoo tunnel. Once the four tunnels are ready, travel time between Jammu and Anantnag will reduce from the current 11-12 hours to 6 hours.

The remaining two tunnels on NH-1 — the strategically crucial Zojila and Z-Morh — will provide all-weather road connectivity between Srinagar and Kargil.
The National Highways and Infrastructure Development Corporation (NHIDCL), a unit of the Ministry of Road Transport and Highways, is implementing all the six tunnel projects, worth Rs 18,539 crore.

“These tunnels are important from a strategic point of view and will provide round-the-year connectivity between Jammu and Kashmir to the rest of India and will also spur economic activity in the region,” NHIDCL managing director Chanchal Kumar told ThePrint.

Kumar added that the tunnels will not only come as a boost for the security forces, but will also ease travel for civilians.

Currently, during the winter, heavy snowfall frequently disrupts road movement on NH-244, connecting Jammu to Anantnag, and NH-1, connecting Srinagar to Kargil.

JK-Tunnels.jpg

Strategic J & K tunnels under construction| Graphics by: Manisha Yadav | ThePrint


Three tunnels to be ready by 2023

Kumar said the three tunnels likely to be completed next year are Khellani, ‘KM 83’, and Z-Morh. The Khellani tunnel is expected to be ready by May and the ‘KM 83’ tunnel by April.

The Z-Morh tunnel, connecting Srinagar to Sonamarg, is likely to be ready by mid-2023. “Though the official date of completion of the Z-Morh tunnel is December 2023, we are hoping to finish work three-four months before the targeted date,” a senior NHIDCL officer said.

The strategically important 14.15 km tunnel coming up at Zojila, connecting Srinagar to Kargil, is expected to be completed by September 2026. The existing NH-1, connecting Srinagar to Leh, remains shut six months on account of snowfall. Once ready, the Zojila tunnel will reduce the travel time between Srinagar and Leh from 3 hours to barely 15 minutes.

The geo-sensitive Zojila stretch, which is strategically important from defence perspective, will not only provide all-weather connectivity between Srinagar, Drass, Kargil and Leh, but also further strengthen economic and social-cultural integration of both the Union Territories.

Bids for two tunnels on NH-244 soon

NHIDCL will shortly open bids for two more tunnels on NH-244 — the 8 km Shudhmahadev-Dranga tunnel worth Rs 3,703 crore, and the 10.3 km Singhpora-Vailoo tunnel worth Rs 4,808 crore.

“We will open the bids soon and intend to award work on both the projects this fiscal,” Kumar said.

Currently, highway projects worth over Rs 50,000 crore are underway in the region and implemented by agencies including NHIDCL and Border Road Organisation (BRO). The BRO and the Public Works Department in Jammu and Kashmir are implementing over 24 NH projects.


@beijingwalker @applesauce @etylo @MH.Yang @Sam6536 @Skull and Bones @Raj-Hindustani @VkdIndian @DabbuSardar @Abu Shaleh Rumi @Bilal9 @SIPRA @Windjammer @Primus @Trango Towers
@FOOLS_NIGHTMARE
@bluesky

BRO ramping up roads in Arunachal districts along LAC

ANI-20221219161747.jpg

BRO developing bordering areas in Arunachal Pradesh to counter China's aggressive behaviour towards LAC (Photo/ANI)

Tezpur (Assam) [India], December 19 (ANI): The Border Roads Organization (BRO) is engaged in major infrastructural development works along the bordering areas and the government has planned to connect all bordering villages of Arunachal Pradesh with good connectivity roads.

Apart from the road connectivity, the BRO is engaging in construction works of two important tunnels in Arunachal Pradesh’s Tawang and West Kameng districts which will become the game changer for the Indian security forces in view of security issues towards the international border.
ANI-20221219112139.jpeg

The BRO has engaged in all infrastructural development works under Project Vartak.

According to the officials, the constitution works of the Nechiphu Tunnel, at an altitude of 5,700 feet, is a unique 500-metre-long “D-shaped, Single Tube Double Lane Tunnel” on the Balipara-Charduar-Tawang (BCT) road in West Kameng district, is nearby of completion and the construction works of the Sela Pass tunnel will also be completed in next 5-6 months.
ANI-20221219112043.jpeg

The Nechiphu tunnel will accommodate two-way traffic and will be equipped with modern lighting and safety facilities and the tunnel has been conceived to bypass extreme foggy conditions prevailing around Nechiphu Pass which have caused hindrance to general traffic and military convoys for many decades.

The Nechiphu tunnel will be provided with a state-of-the-art electro-mechanical system including firefighting devices, an auto illumination system and Supervisory Control and Data Acquisition (SCADA) controlled monitoring systems and it will also accommodate raised footpaths on both sides for safer pedestrian movement which will have ducts for power cables, optical fibre cables and utility lines to strengthen the civic amenities infrastructure.
ANI-20221219112027.jpeg

Under Project Vartak the BRO is also engaged in the construction works of another strategic tunnel, the Twin Tube (1,555 meters and 980 meters) “The Sela Tunnel Project” on the same road.

In an exclusive interview with ANI, Brig Raman Kumar, Chief Engineer, Vartak said that heavy vehicle movement is hampered in the current Sela Pass road during the winter season.

“Now with the construction of the Sela Pass tunnel traffic will be allowed throughout the year. The heavy vehicles whether it is security forces or private industry equipment which is moving to the area will be able to pass easily through the Sela tunnel and accessibility to Tawang will be opened up. As well as it will boost tourism. It is a very important tunnel. The BRO is very happy and proud to give this to the nation,” Brig Raman Kumar said.

He also said that apart from the roads we are having two important tunnels.

“Sela tunnel is under construction and it is about 400 meters below the Sela Pass. We have two tunnels in that alignment. Once that tunnel is completed, we will have throughout the winters also people would be able to pass through the Sela Pass and it will provide good connectivity in the Tawang district. Another tunnel we are having is at Nechiphu. Apart from it, we have bridges, helipads and so many other works which are helped in the overall development of the Tawang district,” Brig Raman Kumar said.

He further said that the Nechiphu tunnel is almost near completion and we are doing the finishing line of the road work. In the next 2-3 months, the Nechiphu tunnel will be opened for public, civilian traffic. The Sela Pass tunnel, it’s a long tunnel – one tunnel is 1590 meter long tunnel and another is almost a kilometre in length the condition in that area is very tough, but BRO is working overnight and 24-hour works are going on and our task is to open the tunnel for the public as earliest as possible.

“In the next 4-6 months we will be able to open the Sela tunnel. We are constructing several permanent bridges in Arunachal Pradesh. Many other bridges are in pipeline,” Brig Raman Kumar said.

The Chief Engineer of Project Vartak said that the BRO is developing and maintaining in all the road networks in important border areas.

“We are part of project Vartak and we are looking after in Western Assam and Western Arunachal Pradesh areas. We have important National Highway double lane roads, and other types of roads and our aim is to connect each and every village in far furlong areas of West Kameng and Tawang district of Arunachal Pradesh. We want to actively contribute to the socio-economic development of this area. The terrain in this area is very difficult. There are mountainous terrain and high altitude terrain. The mountains are very tough and the climate conditions are very tough. The BRO is working round the clock to provide connectivity in difficult and harsh climatic conditions. There are some remote villages and we are also providing roads to the remote villages. There is no area which is not developed part of the Western Arunachal,” Brig Raman Kumar said. (ANI)
Don't care didn't ask
 
TUNNEL.jpg

File photo of Zojila and Z-Morh tunnels | ANI

New Delhi: With the construction of three of the six tunnels, including the strategic Z-Morh tunnel, expected to be completed by mid-2023, road connectivity between Jammu and Kashmir and the rest of India is set to get a big leg up.
Four of the six tunnels are coming up on National Highway-244, connecting Jammu to Anantnag. They are the Khellani tunnel, the KM 83 tunnel, Shuddhmadev-Dranga tunnel and Singhpora-Vailoo tunnel. Once the four tunnels are ready, travel time between Jammu and Anantnag will reduce from the current 11-12 hours to 6 hours.

The remaining two tunnels on NH-1 — the strategically crucial Zojila and Z-Morh — will provide all-weather road connectivity between Srinagar and Kargil.
The National Highways and Infrastructure Development Corporation (NHIDCL), a unit of the Ministry of Road Transport and Highways, is implementing all the six tunnel projects, worth Rs 18,539 crore.

“These tunnels are important from a strategic point of view and will provide round-the-year connectivity between Jammu and Kashmir to the rest of India and will also spur economic activity in the region,” NHIDCL managing director Chanchal Kumar told ThePrint.

Kumar added that the tunnels will not only come as a boost for the security forces, but will also ease travel for civilians.

Currently, during the winter, heavy snowfall frequently disrupts road movement on NH-244, connecting Jammu to Anantnag, and NH-1, connecting Srinagar to Kargil.

JK-Tunnels.jpg

Strategic J & K tunnels under construction| Graphics by: Manisha Yadav | ThePrint


Three tunnels to be ready by 2023

Kumar said the three tunnels likely to be completed next year are Khellani, ‘KM 83’, and Z-Morh. The Khellani tunnel is expected to be ready by May and the ‘KM 83’ tunnel by April.

The Z-Morh tunnel, connecting Srinagar to Sonamarg, is likely to be ready by mid-2023. “Though the official date of completion of the Z-Morh tunnel is December 2023, we are hoping to finish work three-four months before the targeted date,” a senior NHIDCL officer said.

The strategically important 14.15 km tunnel coming up at Zojila, connecting Srinagar to Kargil, is expected to be completed by September 2026. The existing NH-1, connecting Srinagar to Leh, remains shut six months on account of snowfall. Once ready, the Zojila tunnel will reduce the travel time between Srinagar and Leh from 3 hours to barely 15 minutes.

The geo-sensitive Zojila stretch, which is strategically important from defence perspective, will not only provide all-weather connectivity between Srinagar, Drass, Kargil and Leh, but also further strengthen economic and social-cultural integration of both the Union Territories.

Bids for two tunnels on NH-244 soon

NHIDCL will shortly open bids for two more tunnels on NH-244 — the 8 km Shudhmahadev-Dranga tunnel worth Rs 3,703 crore, and the 10.3 km Singhpora-Vailoo tunnel worth Rs 4,808 crore.

“We will open the bids soon and intend to award work on both the projects this fiscal,” Kumar said.

Currently, highway projects worth over Rs 50,000 crore are underway in the region and implemented by agencies including NHIDCL and Border Road Organisation (BRO). The BRO and the Public Works Department in Jammu and Kashmir are implementing over 24 NH projects.


@beijingwalker @applesauce @etylo @MH.Yang @Sam6536 @Skull and Bones @Raj-Hindustani @VkdIndian @DabbuSardar @Abu Shaleh Rumi @Bilal9 @SIPRA @Windjammer @Primus @Trango Towers
@FOOLS_NIGHTMARE
@bluesky

BRO ramping up roads in Arunachal districts along LAC

ANI-20221219161747.jpg

BRO developing bordering areas in Arunachal Pradesh to counter China's aggressive behaviour towards LAC (Photo/ANI)

Tezpur (Assam) [India], December 19 (ANI): The Border Roads Organization (BRO) is engaged in major infrastructural development works along the bordering areas and the government has planned to connect all bordering villages of Arunachal Pradesh with good connectivity roads.

Apart from the road connectivity, the BRO is engaging in construction works of two important tunnels in Arunachal Pradesh’s Tawang and West Kameng districts which will become the game changer for the Indian security forces in view of security issues towards the international border.
ANI-20221219112139.jpeg

The BRO has engaged in all infrastructural development works under Project Vartak.

According to the officials, the constitution works of the Nechiphu Tunnel, at an altitude of 5,700 feet, is a unique 500-metre-long “D-shaped, Single Tube Double Lane Tunnel” on the Balipara-Charduar-Tawang (BCT) road in West Kameng district, is nearby of completion and the construction works of the Sela Pass tunnel will also be completed in next 5-6 months.
ANI-20221219112043.jpeg

The Nechiphu tunnel will accommodate two-way traffic and will be equipped with modern lighting and safety facilities and the tunnel has been conceived to bypass extreme foggy conditions prevailing around Nechiphu Pass which have caused hindrance to general traffic and military convoys for many decades.

The Nechiphu tunnel will be provided with a state-of-the-art electro-mechanical system including firefighting devices, an auto illumination system and Supervisory Control and Data Acquisition (SCADA) controlled monitoring systems and it will also accommodate raised footpaths on both sides for safer pedestrian movement which will have ducts for power cables, optical fibre cables and utility lines to strengthen the civic amenities infrastructure.
ANI-20221219112027.jpeg

Under Project Vartak the BRO is also engaged in the construction works of another strategic tunnel, the Twin Tube (1,555 meters and 980 meters) “The Sela Tunnel Project” on the same road.

In an exclusive interview with ANI, Brig Raman Kumar, Chief Engineer, Vartak said that heavy vehicle movement is hampered in the current Sela Pass road during the winter season.

“Now with the construction of the Sela Pass tunnel traffic will be allowed throughout the year. The heavy vehicles whether it is security forces or private industry equipment which is moving to the area will be able to pass easily through the Sela tunnel and accessibility to Tawang will be opened up. As well as it will boost tourism. It is a very important tunnel. The BRO is very happy and proud to give this to the nation,” Brig Raman Kumar said.

He also said that apart from the roads we are having two important tunnels.

“Sela tunnel is under construction and it is about 400 meters below the Sela Pass. We have two tunnels in that alignment. Once that tunnel is completed, we will have throughout the winters also people would be able to pass through the Sela Pass and it will provide good connectivity in the Tawang district. Another tunnel we are having is at Nechiphu. Apart from it, we have bridges, helipads and so many other works which are helped in the overall development of the Tawang district,” Brig Raman Kumar said.

He further said that the Nechiphu tunnel is almost near completion and we are doing the finishing line of the road work. In the next 2-3 months, the Nechiphu tunnel will be opened for public, civilian traffic. The Sela Pass tunnel, it’s a long tunnel – one tunnel is 1590 meter long tunnel and another is almost a kilometre in length the condition in that area is very tough, but BRO is working overnight and 24-hour works are going on and our task is to open the tunnel for the public as earliest as possible.

“In the next 4-6 months we will be able to open the Sela tunnel. We are constructing several permanent bridges in Arunachal Pradesh. Many other bridges are in pipeline,” Brig Raman Kumar said.

The Chief Engineer of Project Vartak said that the BRO is developing and maintaining in all the road networks in important border areas.

“We are part of project Vartak and we are looking after in Western Assam and Western Arunachal Pradesh areas. We have important National Highway double lane roads, and other types of roads and our aim is to connect each and every village in far furlong areas of West Kameng and Tawang district of Arunachal Pradesh. We want to actively contribute to the socio-economic development of this area. The terrain in this area is very difficult. There are mountainous terrain and high altitude terrain. The mountains are very tough and the climate conditions are very tough. The BRO is working round the clock to provide connectivity in difficult and harsh climatic conditions. There are some remote villages and we are also providing roads to the remote villages. There is no area which is not developed part of the Western Arunachal,” Brig Raman Kumar said. (ANI)


I also big tunnel holes. haha. I am joking. I was actually came here to share https://www.topessaywriting.org/samples/iraq-war website link with you all. Nowadays, there are a lot of burdens on childrens and because of this they can't write their essay on time. Now they can take help from the website given.
I also love big tunnel holes. haha :D
 

Latest posts

Back
Top Bottom