Production of the F-35 Lightning II is on course to make its latest rate rise this year, after Lockheed Martin met its contractual target to deliver 91 of the fifth-generation fighter during 2018.

Detailing last year's delivery total, Lockheed says a combined 54 aircraft were handed over to the US Air Force, US Marine Corps and US Navy, while 21 went to partner nations. The remaining 16 were shipped to Foreign Military Sales (FMS) programme customers.

Lockheed has hailed its achievement of the 2018 delivery target as "demonstrating the F-35 enterprise's ability to ramp up to full-rate production". "Year-over-year, we have increased production, lowered costs, reduced build time, and improved quality and on-time deliveries," notes Greg Ulmer, the company's general manager of the F-35 programme.

That optimism will face a stern test during 2019, however, with an expected 40% increase in output to see Lockheed hand over in excess of 130 units: a rise of at least 39 from last year and roughly double the volume transferred in 2017, when 66 examples were completed.


Flight Fleets Analyzer records a current active fleet of 352 F-35s, assigned to 10 nations. This total includes assets being used in support of initial operational test and evaluation, which are excluded from our annual World Air Forces directory listing.

Our data shows that the US armed services account for 75% of the global F-35 fleet, with the USAF's inventory alone representing a 49% share. Between them, Australia, Israel, Italy, Japan, the Netherlands, Norway, South Korea, Turkey and the UK have received 88 F-35s. The leading international users so far are the UK (17), Norway (16) and Israel (14).

Lockheed uses a further 13 test airframes in support of the programme: five short take-off and vertical landing (STOVL) examples, and four each in the conventional take-off and landing and carrier variant models.

Notable milestones for the programme last year included the completion of its 11-year-long system development and demonstration phase, during which some 9,200 sorties were flown, totalling some 17,000 flight hours.

Production deliveries passed the 300 mark in mid-year and the annual target was met despite the USAF briefly suspending its acceptance of new jets while a contractual dispute was resolved over repairing an exterior panel corrosion issue. The Italian navy, meanwhile, took delivery of its first F-35B from a final assembly and check-out line at Cameri air base

Operational highlights included two air-to-surface combat debuts in the Middle East region, respectively involving the Israeli air force's F-35I "Adir" fleet and the USMC's F-35B.

In Europe, the Italian air force's December declaration of initial operational capability status with its A-model jets was swiftly followed by the Royal Air Force's 617 Sqn achieving the same milestone with its STOVL examples. This followed more UK success, during initial landing trials conducted aboard the Royal Navy aircraft carrier HMSQueen Elizabeth. The Royal Australian Air Force's 3 Sqn also received the nation's first operational F-35As, at its Williamtown base in New South Wales.

Some gloss was removed from these successes, however, when the USMC lost an F-35B during a training flight staged from MCAS Beaufort, in South Carolina - the first crash involving a Lighting II.

Another cause of programme headwinds stemmed from strained relations between the USA and international partner Turkey, which could see Washington DC block the transfer of F-35As to the nation over its planned purchase of advanced surface-to-air missile systems from Russia. Training is, however, still being provided to Turkish pilots and maintainers at Luke AFB, in Arizona.

Regarding future business prospects, Belgium has commenced discussions linked to a potential acquisition of 34 F-35As, having selected the type instead of the Eurofighter Typhoon. The Netherlands is eyeing an increased acquisition, which would boost its eventual fleet size by 15 aircraft, to 52. Japan, meanwhile, has indicated that it could purchase up to another 105 F-35s to meet its future fighter requirements, on top of the 42 to which it has already committed.

Lockheed also appears to be edging closer to agreeing a multi-year contract arrangement with the US Department of Defense, which would support a key programme objective on price reduction. The unit cost for an F-35A in the most recent round of production was $89.2 million, and the company says the programme is "on track to deliver an $80 million" aircraft during lot 14 of low-rate initial production during 2020.

Worth an estimated $22.7 billion, a multi-year deal covering 255 aircraft is now being discussed with the DoD. This proposed total would include 106 for the US services, plus 89 for international partners and 60 for FMS buyers.

https://www.flightglobal.com/news/articles/analysis-f-35-production-ready-to-soar-in-2019-455123/
 
.
Would anybody here know how much time it takes to deliver an F-35 from start to finish? I'm just curious about something, if there is currently an active global fleet of 352 F-35s (and 1 lost), and up to years end 2018 there have been 606 units ordered, there are therefore 263 units currently at some stage of production.

There were 249 units ordered in the years 2017/2018, so by deduction that would mean an average estimate of just over two years to produce each unit. I may be wrong, somebody who knows more could correct me.

If we take Pierre Sprey literally, his prediction about the before 500 unit milestone before the F-35 program is cancelled has already been passed (units ordered).

It is still possible, but highly unlikely, that the program is suddenly cancelled and some of the units currently in production are terminated before 500 units are delivered. Otherwise his predictions are looking exactly like what most rational people thought at the time.
 
.
Would anybody here know how much time it takes to deliver an F-35 from start to finish? I'm just curious about something, if there is currently an active global fleet of 352 F-35s (and 1 lost), and up to years end 2018 there have been 606 units ordered, there are therefore 263 units currently at some stage of production.

There were 249 units ordered in the years 2017/2018, so by deduction that would mean an average estimate of just over two years to produce each unit. I may be wrong, somebody who knows more could correct me.

If we take Pierre Sprey literally, his prediction about the before 500 unit milestone before the F-35 program is cancelled has already been passed (units ordered).

It is still possible, but highly unlikely, that the program is suddenly cancelled and some of the units currently in production are terminated before 500 units are delivered. Otherwise his predictions are looking exactly like what most rational people thought at the time.

Three years apparently, from cutting the first bits of metal to when it leaves the production line.

That 500 jets Sprey talked about was for the US alone, not all countries. But don't take him seriously.
 
.
Production of the F-35 Lightning II is on course to make its latest rate rise this year, after Lockheed Martin met its contractual target to deliver 91 of the fifth-generation fighter during 2018.

Detailing last year's delivery total, Lockheed says a combined 54 aircraft were handed over to the US Air Force, US Marine Corps and US Navy, while 21 went to partner nations. The remaining 16 were shipped to Foreign Military Sales (FMS) programme customers.

Lockheed has hailed its achievement of the 2018 delivery target as "demonstrating the F-35 enterprise's ability to ramp up to full-rate production". "Year-over-year, we have increased production, lowered costs, reduced build time, and improved quality and on-time deliveries," notes Greg Ulmer, the company's general manager of the F-35 programme.

That optimism will face a stern test during 2019, however, with an expected 40% increase in output to see Lockheed hand over in excess of 130 units: a rise of at least 39 from last year and roughly double the volume transferred in 2017, when 66 examples were completed.


Flight Fleets Analyzer records a current active fleet of 352 F-35s, assigned to 10 nations. This total includes assets being used in support of initial operational test and evaluation, which are excluded from our annual World Air Forces directory listing.

Our data shows that the US armed services account for 75% of the global F-35 fleet, with the USAF's inventory alone representing a 49% share. Between them, Australia, Israel, Italy, Japan, the Netherlands, Norway, South Korea, Turkey and the UK have received 88 F-35s. The leading international users so far are the UK (17), Norway (16) and Israel (14).

Lockheed uses a further 13 test airframes in support of the programme: five short take-off and vertical landing (STOVL) examples, and four each in the conventional take-off and landing and carrier variant models.

Notable milestones for the programme last year included the completion of its 11-year-long system development and demonstration phase, during which some 9,200 sorties were flown, totalling some 17,000 flight hours.

Production deliveries passed the 300 mark in mid-year and the annual target was met despite the USAF briefly suspending its acceptance of new jets while a contractual dispute was resolved over repairing an exterior panel corrosion issue. The Italian navy, meanwhile, took delivery of its first F-35B from a final assembly and check-out line at Cameri air base

Operational highlights included two air-to-surface combat debuts in the Middle East region, respectively involving the Israeli air force's F-35I "Adir" fleet and the USMC's F-35B.

In Europe, the Italian air force's December declaration of initial operational capability status with its A-model jets was swiftly followed by the Royal Air Force's 617 Sqn achieving the same milestone with its STOVL examples. This followed more UK success, during initial landing trials conducted aboard the Royal Navy aircraft carrier HMSQueen Elizabeth. The Royal Australian Air Force's 3 Sqn also received the nation's first operational F-35As, at its Williamtown base in New South Wales.

Some gloss was removed from these successes, however, when the USMC lost an F-35B during a training flight staged from MCAS Beaufort, in South Carolina - the first crash involving a Lighting II.

Another cause of programme headwinds stemmed from strained relations between the USA and international partner Turkey, which could see Washington DC block the transfer of F-35As to the nation over its planned purchase of advanced surface-to-air missile systems from Russia. Training is, however, still being provided to Turkish pilots and maintainers at Luke AFB, in Arizona.

Regarding future business prospects, Belgium has commenced discussions linked to a potential acquisition of 34 F-35As, having selected the type instead of the Eurofighter Typhoon. The Netherlands is eyeing an increased acquisition, which would boost its eventual fleet size by 15 aircraft, to 52. Japan, meanwhile, has indicated that it could purchase up to another 105 F-35s to meet its future fighter requirements, on top of the 42 to which it has already committed.

Lockheed also appears to be edging closer to agreeing a multi-year contract arrangement with the US Department of Defense, which would support a key programme objective on price reduction. The unit cost for an F-35A in the most recent round of production was $89.2 million, and the company says the programme is "on track to deliver an $80 million" aircraft during lot 14 of low-rate initial production during 2020.

Worth an estimated $22.7 billion, a multi-year deal covering 255 aircraft is now being discussed with the DoD. This proposed total would include 106 for the US services, plus 89 for international partners and 60 for FMS buyers.

https://www.flightglobal.com/news/articles/analysis-f-35-production-ready-to-soar-in-2019-455123/
 
.
Would anybody here know how much time it takes to deliver an F-35 from start to finish? I'm just curious about something, if there is currently an active global fleet of 352 F-35s (and 1 lost), and up to years end 2018 there have been 606 units ordered, there are therefore 263 units currently at some stage of production.

There were 249 units ordered in the years 2017/2018, so by deduction that would mean an average estimate of just over two years to produce each unit. I may be wrong, somebody who knows more could correct me.

If we take Pierre Sprey literally, his prediction about the before 500 unit milestone before the F-35 program is cancelled has already been passed (units ordered).

It is still possible, but highly unlikely, that the program is suddenly cancelled and some of the units currently in production are terminated before 500 units are delivered. Otherwise his predictions are looking exactly like what most rational people thought at the time.

it takes 41541 man hours to complete 1 F-35A according to a a 2018 GAO report, that's translate to roughly 14 to 18 months per aircraft as of 2018 if they are using 20 workers in the assembly line working between 6 to 8 hours per day 5 days a week (That would be 41700 work hours in total)

https://www.gao.gov/products/GAO-18...ybook&utm_medium=email&utm_source=govdelivery

They are claiming they can make it less than 1 year from rolling into the production line to rolling out in 2020.
 
Last edited:
.
it takes 41541 man hours to complete 1 F-35A according to a a 2018 GAO report, that's translate to roughly 14 to 18 months per aircraft as of 2018 if they are using 20 workers in the assembly line working between 6 to 8 hours per day 5 days a week (That would be 41700 work hours in total)

https://www.gao.gov/products/GAO-18...ybook&utm_medium=email&utm_source=govdelivery

They are claiming they can make it less than 1 year from rolling into the production line to rolling out in 2020.

That's impressive. Do you know if the delivered units require more testing and evaluation, or is all of the testing completed before delivery?
 
.
That's impressive. Do you know if the delivered units require more testing and evaluation, or is all of the testing completed before delivery?

they always require more testing, you cannot test those plane on the ground, so you need to flight test it before delivery.
 
.