What's new

Peshawar BRT project to cost extra Rs2.5bn for completion

At-least after mindlessly criticizing the BRTs and terming it as waste of money PTI have finally realized that BRT are basic need like health for mega cities, If PTI can deliver a good and sustainable BRT which don't need billions in subsidy every year than it's good even in 60 billion. The biggest negative of BRTs of Punjab is that they need huge subsidies to sustain.
 
.
BRT project unlikely to meet April 20 deadline

PESHAWAR: With the April 20 deadline for the launch of the Peshawar Bus Rapid Transit service drawing closer, it seems to be a race against time for the authorities to ensure the project’s completion in the next 50 days.

The PTI-led provincial government had announced that the Rs49 billion flagship project would be successfully executed in six months.

Work on it had begun on Oct 20 last year.

Sources insist frequent changes to design will delay bus service, increase cost by Rs2bn

The sources said the frequent fiddling with the project’s design even several months after its launch was not only going to delay the completion of work but it was also likely to add the over Rs2 billion cost overrun to the project.

“The project’s completion within the deadline seems almost impossible,” a source said.

Last week, project director Sajjad Khan also proceeded on medical leave.

However, the sources attribute his departure to the government’s growing frustration with the project.

Mr Sajjad had overseen the project at the design phase until it was handed over to the Peshawar Development Authority (PDA) for execution.

The officials claimed that Mr Sajjad recently began talking about the course correction in meetings much to the ire of the PDA officials, who considered him to be responsible for planning blunders.

They said the project authorities opined that the PC-I’s revision to enhance the project cost would have to be undertaken at the execution stage due to the unforeseen circumstances, which led to several changes.

A senior government official told Dawn that the exact amount of the revised cost was not clear at the moment as the situation was very much fluid but it was likely to be above Rs2 billion.

The background discussions with the officials paint a picture of a project in a flux with frequent changes and infighting. Sources said that project’s funder Asian Development Bank (ADB) get so much angry with pace of design changes that it fired a nasty email to the project managers chiding them for carrying out alterations with the donor’s approval.

Several sources said the faulty designing process was haunting the project, as large numbers of changes were made to the project, while several others were likely to emerge as the work progressed.

The sources said the detailed engineering design done at the cost of Rs1.253 billion was faulty and was apparently made without keeping ground realities in view.

“The preliminary design accounts for nearly 10 per cent of the detailed design which in turn accounts for up to 85 to 90 per cent of the project,” a source said.

He said at the execution stage, only variations were encountered and minor changes were made to accommodate them.

“What is happening in the Peshawar BRT project are not variations but the wholesome changes,” another source claimed, adding that it would be a blunder when you go for elevated level from ground and construct an underpass instead of elevated section.

The sources said the project has so far faced several major changes which could not have taken place in case it would have been designed meticulously.

“What really happened at design stage was that the designers just drawn lines on google earth but rarely ventured into the field,” a source said, adding that otherwise these changes would not have to be made.

The project designers, sources said that remained unaware of the existence of a 19th century drain, which at the execution stage disrupted their plan to construct a mix traffic underpass at the site. Similarly, they also ignored the fact that a grade level route would close entry and exit points to Gulbahar and Nishtarabad neighborhoods. The contractors first went for grade level route parallel to the Arbab Sikandar flyover but this led to closure of major traffic arteries, forcing the officials to consider building elevated portion next the flyover.

They dug up several piers after this realisation.

However, it had to be abandoned all of the sudden after the ADB objections.

Work on the portion of Pir Zakori Bridge, which will lead the BRT traffic to the GT Road has also yet to start.

Similarly, the construction of another mix traffic underpass at the junction of the Khadim Hussain Road and Airport roads had to be abandoned as it left little room traffic coming towards cantonment area and going to University. It forced the planners to abandon the underpass and go elevated at this spot.

At Gora Qabristan, a nearly completed underpass to be dismantled as due to narrow curve, which could have led to collision of vehicles coming from opposite directions.

On University Road, the authorities decided to construct elevated portion from the KFC to Tambowano Morr after digging of the BRT corridor left only a single lane for mixed traffic.

A source told Dawn that the University Road was likely to have lost parking space after construction of two stations on the main road and it could spell disaster for city’s one the busiest business district.

A senior official associated with the project confirmed a lack of proper planning. “Unfortunately, the planning was not up to the mark,” he said.

Another source told Dawn that the work on two bus depots was yet to start and in their absence it was not clear how the service was going to hit the road.

The haphazard nature of planning can be judged from fact that the authorities had only made token allocation of Rs1,000 as the provincial government share of the project in budget 2017-18.

However, in order to be able to pay for taxes and custom duties on buses, they have to rush to provincial cabinet to approve over Rs. 5 billion as supplementary grant.


Ironically, an army of the project’s staff members is drawing from Rs5,000 to Rs300,000 a month as BRT allowance since Dec 2016.

The details available with Dawn show that the number of the buses has also been reduced from 299 to 220 and the contract has been awarded to a Chinese company Xiamen Golden Dragon Bus Company, which offered lowest bid of Rs5.478 billion for supplying buses.

Transport secretary Kamran Rehman denied the reports of cost escalations, saying PC-I is revised in case of difference between costs and estimates and currently there was no need for it.

He also denied reports of Mr Sajjad removal and said he was very much part of the project.

When contacted, PDA director general Israrul Haq said the authority had completed around 50 per cent work on the project.

He said he was hopeful that the project would be completed on time.

“We have not changed the deadline. Any change will be made keeping the project progress in view,” he said.

Mr Israr said changes to the design were routine issues, which arose from time to time and were decided accordingly.

About the revision of the project’s PC-I, he said it was very big and complex project, its PC-I’s revision was an ongoing process.

The PDA chief denied any cost overrun at the moment.

“I have no knowledge of it (cost overrun),” he said.

Mr Israr also denied reports of difference of opinion with the ADB on the project.

Published in Dawn, March 2nd, 2018

https://www.dawn.com/news/1392589/brt-project-unlikely-to-meet-april-20-deadline
 
. .
Last edited:
.
in current political corrupt system no matter how honest a person is he cannot control corruption due to corrupt electives who change parties to remain and govt for their business.govt is now become a business.
 
. .
Hm things are not good as they are shown on social media
Absolutely, check this video from 23 oct 2017 and observe the condition of streets and markets of Peshawar alone the provincial capital of KPK...


plus this report from frontier post, the news paper belonged to Peshawar KPK..

https://thefrontierpost.com/350-dams-kp/

these are just glimpses of the current situation of KPK right now, i tell you the ground situation in kpk is much much different, than being portrayed on social media...
 
.
Absolutely, check this video from 23 oct 2017 and observe the condition of streets and markets of Peshawar alone the provincial capital of KPK...


plus this report from frontier post, the news paper belonged to Peshawar KPK..

https://thefrontierpost.com/350-dams-kp/

these are just glimpses of the current situation of KPK right now, i tell you the ground situation in kpk is much much different, than being portrayed on social media...
Agree sir . I think there is alot of propaganda on social media
 
. .
Design changes to delay Peshawar BRT project

PESHAWAR:

With the provincial government hoping that the BRT does for them what the Metro Bus project in Punjab did for the PML-N in the last general elections, a senior engineer working on the project in Peshawar has warned against constant tinkering in the design of the project to make sure it is completed on time.

When work on it first started in October last year, Khyber-Pakhtunkhwa (K-P) Chief Minister Pervez Khattak had promised that the project would be completed within six months. But as that deadline nears, the project looks far from being complete.

The Project Management and Construction Supervision Consultant (PMCSC) for the Peshawar Bus Rapid Transit (BRT) project have written a letter to the director general of the Peshawar Development Authority (PDA) stating that the contractor working on building the project must be given a clear sense of direction to complete his work.

Lack of coordination: Too many departments spoil the project

“The continuous amendments to the design of various aspects of the Peshawar BRT project is seriously jeopardising the completion of the Peshawar Sustainable BRT Project within the specified time limits,” the letter warns, adding that not only are the extensive design changes causing setbacks, the time it takes the government machinery to approve these changes was even more agonising — as it alluded to the lack of any decision-making power of the chief engineer.

Khattak has been pushing the private contractor and other government bodies working on the BRT to complete the Rs49.3 billion project by April 20 so that he can inaugurate it before the end of his tenure. But constant changes have made the task of achieving that target impossible.

The letter, written by an engineer of the private consultancy firm contracted for the project adds, “Neither timely approvals are forthcoming from the approving agencies nor are the conceptual designs, being provided by others for major design amendments, are — in nearly all instances — workable for one reason or another, and require reworking according to site conditions before being buildable.”

The firm has asked the government to intervene and put a halt to any further design amendments so that the contractor and the government can concentrate on completing the project without any unnecessary distraction.

In just the six months since the government started work on the project, the project design has been changed at 11 different points.


As a result, work on several sections of the project has yet to get underway such as work on the Gulbahar flyover.

The government had initially decided to build a BRT corridor here at ground level. However, the designers later realised that this would rob Gulbahar and Sikandpur residents of key U-turns while the existing Arbab Sikandar Khan Khalil flyover would lose its utility. The design was hence altered.

Green Line BRTS faces delay due to design change

Similarly, work on the Level-II Pir Zakori Bridge has yet to start. Construction of the elevated corridor in Tehkal was decided months after the civil work on the project kicked-off.

Later, with work on an underpass at Aman Chowk almost complete, it had to be dismantled and rebuilt owing to design flaws. Moreover, the government has now decided to make a station at Karkhano Market.

Officials working on the project say that the constant changes in the design are not only delaying the project but are also adding to its cost.

“At the moment, the cost is still Rs49.3 billion, but it will certainly increase by about a billion or more because of the additional elevated portions which were added later,” the official said, adding that even with everyone working on the project being pushed to their limit, the April 20 deadline seems almost impossible to meet.

“Officials have started to squabble in meetings as the deadline looms,” said a senior government official dealing the matter. He pointed to a brawl between the PDA director general and DIG traffic during a recent meeting on devising a traffic management plan.


The official divulged that an irate DIG Traffic had turned around to lambast PDA chief of focusing on BRT project and completing it as soon as possible.

“People have started to realise that the deadline is not going to be met, thus they have started skipping meetings,” said the official.

PDA admits delays

Meanwhile, PDA Director General Israrul Haq has admitted that the project is facing delays and that people should not expect it before May 20, a month over its prescribed deadline.

“Our deadline for the contractor is April 20, and we are pushing [hard] to achieve it. If it gets late it will not be more than a month,” Haq said as he insisted that they were doing all they can to meet the deadline.

Referring to the changes, Haq termed them as ‘minor’.

“You make changes even while building a small bathroom in your home, this, though, is a mega project and it will certainly undergo structural changes,” he stated matter-of-factly.

The PDA chief added that work on the Pir Zakori Bridge is expected to start in a day or two and the project will be completed within three months. However, he was quick to clarify that the bridge is not a part of BRT, thus it will not affect that project’s overall completion deadline.

He also admitted that the cost of the BRT project will rise due to the design changes, but he tried to downplay them by terming them ‘nominal escalation which promises more benefits’.

Published in The Express Tribune, March 14th, 2018.

https://tribune.com.pk/story/1659178/1-many-cooks-design-changes-delay-project/
 
.

Latest posts

Pakistan Affairs Latest Posts

Back
Top Bottom