What's new

Daanish school building crumbles within a year of opening

pkuser2k12

SENIOR MEMBER
Joined
Oct 28, 2012
Messages
6,460
Reaction score
3
Country
Pakistan
Location
Pakistan


55924a44b9a4e.jpg




LAHORE: Within a year of its inauguration, the building of Daanish school in Attock district has started crumbling, with major cracks in walls and beams and leaking pipes and roofs – forcing management to close down its two dining halls.


A report by the Chief Minister Inspection Team, which investigated the faults and causes at the Malala Yousafzai Daanish School in tehsil Jand, Attock, says: “The errors (cracks) that have appeared in these buildings are of serious and unique nature and cannot be rectified with confidence. Precious lives are at stake, which cannot be left to chance.” Thus partial closure of the residential school has been ordered by the Daanish Schools Authority.

The report has raised serious concerns about soil survey, building and structural design, material used in the buildings and non-supervision of the work, terming all these factors major causes of the start of collapse of the building that had cost the nation Rs698m within a year.

The school was inaugurated by Chief Minister Shahbaz Sharif on Feb 14, 2013, and the cracks in the building started appearing in February 2014. They were still being rectified when “major and minor cracks appeared in all the walls and floors. February this year, cracks in structural beams of the dining halls appeared,” ringing the alarm bells in official circles.

Nespak responsible for structural flaws: CMIT report

Basing its conclusion on observation of three professionals, who were part of the investigation, the report says: “The defects in the building are (result of) structural failure and non-vetting of design and structural designs by the third party. There was no mechanism in place to counter-check plans prepared by the consultant.”

Holding National Engineering Services Pakistan (Nespak), the consultant, responsible for the faults, the reports says “Nespak did not point out structural design deficiencies and flaws during the entire period of execution. The resident supervision has been carried out in mechanical manners, without any comprehensive and meaningful input on the design of the project.”

The inspection team asked for the complete set of drawings, complete structural design calculations and computer model of the project and found them missing with all the concerned// yahan b form 15 wala kam ho gaya// – the Daanish Schools Authority, the consultant, the contractors and the sub-contractor.

Apart from Nespak, “the general manger (engineering) of Daanish authority can also be held responsible for not examining structural designs and point out shortcomings in structural drawings provided by the consultant. The design was squarely left to the consultant, and there was no checking and vetting mechanism in place.”

About the process of awarding contract, the reports says that P&D guidelines were not followed when hiring consultants
– for planning, designing, estimation, preparation for tender documents and detailed drawings. When the P&D raised its objections for ignoring its guidelines, the chief minister provided an administrative waiver. When the P&D raised the issue of transparency, the then chief secretary wrote: “The proceedings undertaken so far have been under my direct supervision, the transparency is thus (automatically) assured,” and the CM granted another waiver.

About the causes of building collapse, the report says that geotechnical investigations were not carried out at the building site. Since the building is situated in the Pothohar, the soil investigation was all the more necessary. The available soil survey is of a site almost a kilometer away from the building. To make the matter worse, 37pc material used in the project was not up to the tendering documents’ mark and is now simply falling apart. Because of quality of material, diagonal cracks have appeared in walls, shear and bending cracks in RCC (roller-compacted concrete) beams in dining halls of hostels, settlement of floors, leakage in sewer pipes, problems with slopes of roof treatment while cladding is not properly installed. Even roots of trees were not fully removed before the construction.

About the contractor, the report maintains that “visits to the site and test reports by the Building Research Station prove inferior workmanship and use of low quality material, which is now resulting in leaking of roofs, major and minor cracks in walls and beams and submerging of floors. Proper specifications were provided in tender but they were not implemented by the contractors.”

“The fast track project is falling apart even faster,” comments an official involved in the investigation. The problem is that Nespak, headed by a strongly connected person, is the culprit. Had it been any other government agency, dozens of arrests could have been made by now. In this matter, the CM is forming one committee after another despite the facts being fully known to him, he claims.



Published in Dawn, June 30th, 2015

Daanish school building crumbles within a year of opening - Pakistan - DAWN.COM



 
. .
DFM on Showbaz and Punjab Govt. This one building had cost the nation whooping Rs 698m and it crumbled within a year.. Brilliant job @Muhammad Omar @SBD-3 @cb4 @Tameem @AdeelFaheem @I FLY HIGH

The Article said NESPAK is the Responsible for structural flaws just like NLC was responsible when the bridge collapsed in Karachi Shershah but no one fingered sindh gov ? poor Work in Rawalpindi section of Metro done by NLC

NESPAK made many good building even NLC but they are also corrupt....

now you will say why gov choose NLC and NESPAK for these project if they are corrupt and work quality is slow and Shit
my answer willl be Ask KPK that ques to they Gave project of Bab-e-Peshawar to NLC you will see their shit quality work soon....
 
.
The Article said NESPAK is the Responsible for structural flaws just like NLC was responsible when the bridge collapsed in Karachi Shershah but no one fingered sindh gov ? poor Work in Rawalpindi section of Metro done by NLC

NESPAK made many good building even NLC but they are also corrupt....

now you will say why gov choose NLC and NESPAK for these project if they are corrupt and work quality is slow and Shit
my answer willl be Ask KPK that ques to they Gave project of Bab-e-Peshawar to NLC you will see their shit quality work soon....



haha, so we should expect some strong action against NLC / NESPAK soon? Do update us on that action if its ever going to happen. And we should also expect NLC / NESPAK being barred from future contracts, no?
 
.
haha, so we should expect some strong action against NLC / NESPAK soon? Do update us on that action if its ever going to happen. And we should also expect NLC / NESPAK being barred from future contracts, no?
LOL, Do you know who runs NLC and NESPAK?
 
. .
......

A report by the Chief Minister Inspection Team, which investigated the faults and causes at the Malala Yousafzai Daanish School in tehsil Jand, Attock, says:

Please note

A report by the Chief Minister Inspection Team.
 
.
haha, so we should expect some strong action against NLC / NESPAK soon? Do update us on that action if its ever going to happen. And we should also expect NLC / NESPAK being barred from future contracts, no?

Yes NLC didn't get part of Multan Metro which is under construction they want some of it's packages... Did you expect Action against them? i don't think so as NLC and Nespak are running by Generals... Army se panga kaun le?? :disagree::disagree::disagree::disagree::disagree: :lol::lol::lol::lol:
 
. .
Please note

A report by the Chief Minister Inspection Team.

Chief Minister Inspection Team also pointed out many flaws in Rawalpindi metro section Saddar and Shahbaz Shareef reported to General about their work quality and not happy with them even because of NLC didn't finished it's work of sewerage system the water was found in the underground passageway
 
.
that is why i underlined it .so that pmln walas dont dub it as biased media reporting

Bhai jaan,

you had a point If CM Punjab was ignorant dumb and dumber

But if the poor thang is sending out inspection teams, keeping an eye on things, you should appreciate it. That he is on top of things.

CM is not hiring concrete mixer guy. Some local contractor did. And things got substandard. CM found it so now give his system time to fix things.

This is not a $tupid discussion between PTI and PPP PMLN.

This is about fixing a system.

So please be serious.
 
.
Bhai jaan,

you had a point If CM Punjab was ignorant dumb and dumber

But if the poor thang is sending out inspection teams, keeping an eye on things, you should appreciate it. That he is on top of things.

CM is not hiring concrete mixer guy. Some local contractor did. And things got substandard. CM found it so now give his system time to fix things.

This is not a $tupid discussion between PTI and PPP PMLN.

This is about fixing a system.

So please be serious.

and if cm wanted to fix the system this would not have been in the news i posted above

About the process of awarding contract, the reports says that P&D guidelines were not followed when hiring consultants – for planning, designing, estimation, preparation for tender documents and detailed drawings. When the P&D raised its objections for ignoring its guidelines, the chief minister provided an administrative waiver.

When the P&D raised the issue of transparency, the then chief secretary wrote: “The proceedings undertaken so far have been under my direct supervision, the transparency is thus (automatically) assured,” and the CM granted another waiver.

The problem is that Nespak, headed by a strongly connected person, is the culprit. Had it been any other government agency, dozens of arrests could have been made by now. In this matter, the CM is forming one committee after another despite the facts being fully known to him, he claims.


From:

Daanish school building crumbles within a year of opening - Pakistan - DAWN.COM
 
.
Chief Minister Inspection Team also pointed out many flaws in Rawalpindi metro section Saddar and Shahbaz Shareef reported to General about their work quality and not happy with them even because of NLC didn't finished it's work of sewerage system the water was found in the underground passageway
blame CM if things do not get fixed.

If he is trying to find weak points and issues, do not jump on his back.

and if cm wanted to fix the system this would not have been in the news i posted above

you are being partisan now.
 
.
blame CM if things do not get fixed.

If he is trying to find weak points and issues, do not jump on his back.



you are being partisan now.

when P&D raised objections the cm gave waiver twice first on granting the project and not following guidelines and then on transparency and now when cm found the culprit nespak he is forming committees on committees and not punishing the culprits who wasted 680m and that too on a project solely for poor children's education not for some fancy yo yo elite children
 
.
blame CM if things do not get fixed.

If he is trying to find weak points and issues, do not jump on his back.



you are being partisan now.

Finding weak points and issues one year after children have been going there?

About the process of awarding contract, the reports says that P&D guidelines were not followed when hiring consultants – for planning, designing, estimation, preparation for tender documents and detailed drawings. When the P&D raised its objections for ignoring its guidelines, the chief minister provided an administrative waiver. When the P&D raised the issue of transparency, the then chief secretary wrote: “The proceedings undertaken so far have been under my direct supervision, the transparency is thus (automatically) assured,” and the CM granted another waiver.

You can not blame people for being partisan. You have to call a spade out sometime.
 
.
Back
Top Bottom